TIPS for Above and Below Ground GRP Pipe Installation

by Dec 18, 2019Product Sourcing and Supervision Services

TIPS for Above and Below Ground GRP Pipe Installation

 

I compiled a collection of tips that I believe would be helpful for you. The installation of GRP pipes above and below ground can be tricky, but following these tips should ensure that you have a smoother installation.

 

Let’s first talk about laying GRP pipes above the ground!

 

The distance between the supports, the type of supports, the anchorage and the fixing points are defined in the design stage. In general, pipes should be supported by concrete cradles surrounding the pipes over an arc of 150° with a layer of rubber in between, which is at least 4 mm thick.

During the laying operations, it is necessary to take all possible precautions to avoid damaging the product. In particular, you should keep in mind the following steps:

  • tightening of the fixed points (clamps) should be carried out with the pipe at the temperature that is expected during the working conditions; the design values should be meticulously respected;
  • bolts of flanges should be tightened at the specified loads;
  • elbows should be anchored when it is foreseen that the pipe will undergo torsion stresses;
  • fittings not made of FRP, such as valves, steel flanges, and the like, should be supported individually;
  • battery limits made of different materials, such as connections to equipment or pipelines, should not transfer additional stresses to the FRP pipeline;
  • all tee connections should be supported in order to avoid interactive stresses between the main line and the branch lines.

 

You have to keep in mind, that these are general tips and do not cover all of the problems associated with the laying of pipes above ground. Therefore, during the design stage, stress should be analysed for each individual case and the most suitable support system should be selected. Furthermore, when pipes are installed in contact with the flammable products, all metal parts should be earthed to prevent the build-up of the electrostatic charges leading to sparks.

 

Now, what about laying GRP pipes below ground?

 

The underground pipes are laid on a bed of sand or screened material, compacted to the level anticipated in the design. Then, the backfilling is carried out at the sides and above the pipe in layers of 20-30 cm, with the same material as was used for the bed.

 

The first layer of the backfill should be applied with great care, since it provides a firm support under the pipe. Each layer must be compacted with the methods and systems adapted to the nature of the material employed, taking care to avoid any damage to the pipe during this operation. It is beneficial to increase the vertical diameter of the pipeline during the laying operations for 1% – 3%, in order to compensate for the reduction of the vertical diameter, which occurs during the pipeline operation.

 

Like with the above-ground installation, it is not possible to provide full instructions for the below-ground laying operations, since each installation has different requirements, but the following recommendations can be very useful:

  • the trench walls should be dug as vertical as possible;
  • any contact between the pipe and large stones or rocks should be avoided;
  • in case of the installations below the water table, continuous drainage should be provided in the trench until the backfilling has been carried out;
  • crossing areas, subjected to heavy external loads (permanent or mobile), must be very carefully analysed to establish if special steps have to be taken, e.g. different stiffness to fit the situation, increased burial depth, use of a sheet metal or a reinforced concrete cover;
  • in soils with a low modulus of reaction, such as clayey soil, or grounds with a high content of organic substances, the width of the trench should be increased and pipes should be surrounded with the compacted and selected backfilling material;
  • the behaviour of the underground pipes is greatly affected by the surrounding soil. When carrying out the laying  operations, it is therefore essential to comply with the requirements of the design.

An engineer designing the underground pipelines should take great care in examining the soil parameters. In case they have any doubts, they should assume the worst possible conditions.

 

Do you have any questions or concerns about your pipe installation?

 

Feel free to contact us by simply completing the form below and we will help you out!

7 + 6 =

Related Posts

TIPS for Above and Below Ground GRP Pipe Installation

I compiled a collection of tips that I believe would be helpful for you. The installation of GRP pipes above and below ground can be tricky, but following these tips should ensure that you have a smoother installation.

TESTIMONIALS

Effective Filament Winding testimonials

POPULAR BLOG POSTS

ARCHIVES